It’s the second week of January. The first site opens on Monday morning and the cool room alarm is going. The second site has a roller door that won’t lift because the motor tripped during a storm on Boxing Day. The third site is fine, but a leaking tap reported on 19 December is still leaking, because the job was raised and nobody booked it before the break.

Most of that is avoidable. A Christmas shutdown is a short project for every site at once: decide what closes, what stays on, who can get in, which jobs finish first, and what gets checked before people come back.

This checklist is for operators running more than one site. It isn’t legal or employment advice. Your award, your lease and your insurer come first.

Six to eight weeks out: set the dates and the notice

  • Set the closing and reopening date for each site. Sites don’t always close on the same days. Write each one down.
  • Check the notice rules that apply to your staff. Many modern awards set out how much written notice you must give before a close-down. Check your award and the Fair Work Ombudsman’s guidance now, because notices for late December closures are due around this time.
  • Tell your landlords and building managers which days each site is closed and who to contact.
  • Tell your regular contractors per site and per trade when each site closes and reopens, so planned visits aren’t booked into a locked building.

Four weeks out: clear the open jobs

The most common reopening problem is a job that was raised before the break and never finished.

  • List every open maintenance job for every site. Sort it by priority: anything affecting safety, security, cold storage or water comes first.
  • Book the jobs that must finish before closing, such as a door that doesn’t lock, a failing heating and cooling unit or a leaking pipe.
  • Decide which jobs can wait until January, and give each one a booked date in the first week back rather than leaving it open with no date.
  • Bring forward planned servicing that falls due over the break, such as fire equipment, backflow testing or refrigeration servicing, where a visit can’t happen with the site closed.

The week before: what stays on and who can get in

For each site, write down:

1. What stays powered. Fridges and cool rooms, alarms, security cameras, server cabinets, sump pumps and any plant that must keep running. 2. What gets switched off or isolated. Hot water units that won’t be used, non-essential lighting, office equipment, and irrigation if it isn’t needed. 3. Who holds the keys and alarm codes, and their phone number over the break. 4. Who is on call for each site and each kind of fault: power, water, security and refrigeration. 5. Which contractor attends an emergency at that site for each trade, and the after-hours number to call. 6. What to do in a storm. Summer is storm season in much of Australia. Clear gutters and drains before closing, tie down or bring in outdoor items, and know who checks the site after a severe storm warning. Our storm season checklist covers each step.

Put the list on the board or in the shared drive for every site, not in one person’s head.

The last day: the walk-through

A short walk-through on the last day catches most problems:

  • Doors, windows and roller doors locked; alarm set and the monitoring company told the site is closed.
  • Taps off, no running toilets, no leaks under sinks.
  • Fridges and cool rooms at temperature, with anything perishable removed if the site won’t be checked.
  • Bins emptied, with no food waste left inside.
  • Photos of each area, so there is a record of the condition the site was left in.

Over the break: when something goes wrong

Faults still happen when a site is closed. A neighbour reports water running out of a downpipe. The alarm monitoring company calls about a door. Whoever is on call needs to know who to book for that site and trade, and the job should be raised and tracked like any other, so it doesn’t get lost in a text message on 27 December.

The first week back: reopening checks

Before staff return to each site:

  • Walk through each site a day or two before it opens, if you can.
  • Check refrigeration temperatures and the alarm log for any power loss.
  • Run the taps and check hot water.
  • Check for leaks, storm damage and pests.
  • Test the heating and cooling, especially in sites that heat up fast when closed.
  • Book every fault found straight away, to your own team or your contractors.
  • Close out the jobs you held over from December on their booked dates.

If a site lost power over the break, run the power outage checklist before restocking.

Running the shutdown on one OpsChase board

OpsChase is one AI-powered platform for running maintenance across one site or many. Over a shutdown, it keeps every site’s jobs in one place:

  • Anyone can raise a fault from their phone, with photos, whether it’s a site manager in December or the on-call person over the break.
  • Jobs are booked to your own team or your contractors. Set your regular contractors per site and per trade, such as the refrigeration firm, the plumber and the electrician for each site, so each job goes to the right preferred contractor.
  • Each job is tracked until the work is done, then closed with proof of completion: photos and sign-off on the work order.
  • Keep licence, public liability, induction and site-access details on file for each contractor firm through contractor compliance, so the team can check them before booking a visit to a closed site.

With Assets & planned maintenance switched on, each cool room, heating and cooling unit, hot water system and roller door has its own service history, and planned maintenance runs through scheduling, so servicing due over the break can be moved to before closing or the first week back.

What the manager sees

Across every site, the manager sees one board:

  • Every open job, by site, sorted by priority.
  • Jobs booked before closing and jobs booked for the first week back.
  • Faults raised over the break and who is booked to attend.
  • Late jobs showing against your response targets.

For more on running several sites from one view, see multi-site maintenance and facilities maintenance.

Where to start

Today, list every site with its closing and reopening date, and every open job at each one. Book the jobs that must finish before the break, and give the rest a date in January. Then see how OpsChase handles it on pricing, or book a demo with a list of your sites.

A shutdown that is planned site by site means the first Monday back is a normal Monday, not a week of catching up.

Related on OpsChase

Questions

Who raises a fault when a site is closed for Christmas?
Whoever finds it: the on-call person, a key holder doing a check, or a site manager after a call from the alarm monitoring company. They raise it from their phone with photos, and the job is tracked until the work is done.
How do jobs book to the right contractor per site and trade over the break?
Set your regular contractors per site and per trade, such as the refrigeration firm, plumber and electrician for each site, so a fault at a closed site goes to the right firm for that site and that kind of work.
What stays in our own systems?
Rosters, leave, payroll and shutdown notices to staff stay in your own human resources and payroll systems. OpsChase holds the maintenance side: faults, booked jobs, planned servicing and proof each job was done.
What does the manager see across sites during the shutdown?
One board with every open job by site, sorted by priority, the jobs booked before closing and for the first week back, faults raised over the break, and any late jobs showing against your response targets.